Phase II work is underway for the Campus Center project including demolition and rebuild of Stamps Commons and renovation of the Wenn Student Center.
General:
*Surface Lot 2 and Student Center parking deck remain open for public use.
*Heavy construction traffic in this sector of campus.
*Normal working hours are Monday - Saturday 6:00 AM – 5:30 PM.
Arts Plaza Exterior Work:
*Pavers and sidewalk in front and around the Ferst Center Arts Plaza is complete.
*Fencing has been modified to open up Ferst Center front doors and the connecting pathway around the Ferst Center for the Arts.
Phase II Building Construction:
*Construction fencing is installed around perimeter of the site. Wayfinding signage is installed.
* Demolition of the Stamps Commons building is ongoing, the above grade structure has been demolished with only the post office and foundations remaining.
* Pedestrians to be aware of high truck traffic leaving the loading dock of the existing Wenn building as debris is hauled off site.
* Interior demolition of the Wenn Student is underway.