Campus Center construction continues through the month of December.
In the month of December 2019, Phase I work including construction of the Exhibition Hall, Pavilion and Café buildings will continue for the Campus Center project.
General:
*Construction truck traffic in this sector of campus.
*Normal working hours 6:30 AM – 5:30 PM.
Phase I Building Construction (within project fence line):
*Pre- Engineered Metal Buildings and roofing for Pavilion buildings will be erected.
*Exterior metal framing, sheathing, and waterproofing at Café building will be installed.
*Waterproofing, flashing, masonry and windows will be installed at Exhibition Hall.
*Overhead mechanical, electrical, and plumbing systems at the Exhibition Hall installation will continue.
*In- wall electrical and plumbing systems at the Exhibition Hall installation will continue.
*Underground domestic water and fire line service will be installed.
Phase I Utilities:
*Storm, sanitary sewer, and power ductbank will be installed north of the Student Center Parking Garage 9/6/2019 – 12/20/2019.
*Fencing will remain in place to provide barriers between construction activities and the campus.
*Signage will remain in placed around perimeter of fencing to direct pedestrian traffic.
*Pedestrian pathways approaching Ferst Center from ISYE lawn have been installed to divert walkways around construction.
*Way finding signage has been placed around this part of campus to provide alternate routes.
*ADA pathways will be maintained from the parking lot in front of Student Services to Ferst Center for the Arts.
Phase II Existing Utilities Site Investigation:
*At the Campanile Plaza area, site investigations to verify and confirm locations of existing underground utilities will be performed.
*Temp barricades and signage will be placed around work perimeter to direct pedestrian traffic.
*Small localized excavations using a hydrovac truck will be mobilized.
*The hydrovac truck will access the work area from the W21 parking lot. Subsequently, 3 parking spaces in the extreme south end will be closed for staging.
*Small areas will be cut into the turf and landscape areas. These areas will be backfilled and patched once investigations are complete.
*Site logistics plan is attached.
Old OIT Engineering Building – Temp WREK Radio:
*Miscellaneous interior renovations including new walls, electrical, and HVAC work will occur during the months of December and January.
*Areas of the building’s adjacent parking lot will be dedicated to Contractors and logistics.