Utility implementation surrounding Tech Square Phase 3 continues through June.
May 14, 2024
Utility work on Fifth St. is underway and based on the receipt of the work permit for Biltmore Place, utility work is anticipated to begin there on Monday, May 20. Work on Biltmore Place will happen concurrently to the work on 5th street.
BILTMORE UTILITY WORK:
- Permit for work on Biltmore Place is pending
- Duration of work will be approximately 4 weeks
- LOGISTICS
- Biltmore Place will be closed from 7 a.m. – 4 p.m. Outside of those hours, it will be open with metal plates on the street.
- Eastbound vehicular traffic will detour to Armstead Place, while westbound vehicular traffic will detour to Abercrombie Place.
- Biltmore Place will be unavailable to bike and pedestrian traffic. All bike and pedestrian traffic between Spring St. and W. Peachtree St. will flow through the sidewalk on the south side of Fifth Street.
We appreciate your patience and flexibility as we move further along in this construction project. Should you have any questions, please reach out.